Description
Prepare the MAgnesium SR1 release .
This means to:
- cherry-pick related bug corrections from master , improvement on OTN and T-API are concerned
- update project version in poms
- update dependencies
- update others environment parameters e.g. for lighty.io and tox
Once that done, the release must be staged in Jenkins and then officially released using the self-service process
https://docs.opendaylight.org/en/stable-magnesium/release-process/project-release.html
This last task can only be performed when all upstreams dep are ready i.e. when all managed projects have been released (prevision date 04/20/2020).
The deadline is one week after all managed projects have been released.
Evaluation indicators:
- cherry-picks from master done
- magnesium stage release job OK in Jenkins
- tpce artifacts published on nexus