[TRNSPRTPCE-336] Prepare Al SR1 release Created: 12/Oct/20  Updated: 03/Sep/21  Due: 05/Nov/20  Resolved: 09/Nov/20

Status: Verified
Project: transportpce
Component/s: None
Affects Version/s: None
Fix Version/s: None

Type: Task Priority: High
Reporter: Guillaume Lambert Assignee: Gilles Thouenon
Resolution: Done Votes: 0
Labels: None
Remaining Estimate: 1 day, 5 hours
Time Spent: 1 day
Original Estimate: 2 days, 5 hours

Epic Link: ODL and LFN process

 Description   

Prepare the Aluminium SR1 release
( device model 7.1 support may be needed for flexgrid since manufacturer devices don't propose it with previous versions - it can be integrated with SR2)

This means to:

Once that done, the release must be staged in Jenkins and then officially released using the self-service process

https://docs.opendaylight.org/en/stable-aluminium/release-process/project-release.html

This last task can only be performed when all upstreams dep are ready i.e. when all managed projects have been released (prevision date 10/30/2020).
The deadline is one week after all managed projects have been released.

Evaluation indicators:

  • cherry-picks from master done
  • magnesium stage release job OK in Jenkins
  • tpce artifacts published on nexus