[TSC-119] TSDR slow to sign-off CSIT failure for Oxygen SR2 Created: 12/Jun/18  Updated: 05/Jul/18  Due: 05/Jul/18  Resolved: 05/Jul/18

Status: Closed
Project: tsc
Component/s: None
Affects Version/s: None
Fix Version/s: None

Type: Grievance Priority: Low
Reporter: Daniel Farrell Assignee: Unassigned
Resolution: Done Votes: 0
Labels: None
Remaining Estimate: Not Specified
Time Spent: Not Specified
Original Estimate: Not Specified

ODL Project: tsdr
ODL Release:

 Description   

As noted in this thread, TSDR was slow to sign off on their CSIT failures for Oxygen SR2. It took four business days for the project's PTL to speak up and sign-off. The required response time is two business days.

TSDR is not a Managed project, and Oxygen is the last release to not use the Managed Release Model, but we're still filing a grievance to make it easier to track this later.



 Comments   
Comment by Scott Melton [ 27/Jun/18 ]

We had forgotten about the new (newly enforced?)  two day deadline for updating the spreadsheet.  We were working the issues and hoped to have them fixed before we updated the spreadsheet.  If there are other requirements on TSDR in the future we will do our best to meet them.

Comment by Daniel Farrell [ 27/Jun/18 ]

Managed Projects should be responsive over email, IRC, Gerrit, Jira and in regular meetings.

All committers should be subscribed to their project’s mailing list and the release mailing list.

For the following particularly time-sensitive events, an appropriate response is expected within two business days.

  • RC or SR candidate feedback.
  • Major disruptions to other projects where a Jira weather item was not present and the pending breakage was not reported to the release mailing list.

https://docs.opendaylight.org/en/latest/release-process/managed-release.html#responsiveness

No worries, it's newly specific and new that we're tracking it. 

Comment by Scott Melton [ 05/Jul/18 ]

I just saw Abhijit's email about the Flourine middle checkpoint grievance list.  I have a prior commitment and will not be able to attend the TSC meeting.  Please accept my reasons for our lack of response as stated above.  I will review the meeting minutes and address any issues.  Thanks!

 

Comment by Daniel Farrell [ 05/Jul/18 ]

No worries scottmelton, thanks for letting us know. I think since TSDR is Self-Managed this is more docs than something we really need to do anything substantial about.