[TSC-66] COE joining Managed Release for Fluorine Created: 23/Mar/18 Updated: 06/Apr/18 Resolved: 06/Apr/18 |
|
| Status: | Closed |
| Project: | tsc |
| Component/s: | None |
| Affects Version/s: | None |
| Fix Version/s: | None |
| Type: | Project Plan | Priority: | Medium |
| Reporter: | Prem Sankar Gopannan | Assignee: | Daniel Farrell |
| Resolution: | Done | Votes: | 0 |
| Labels: | None | ||
| Remaining Estimate: | Not Specified | ||
| Time Spent: | Not Specified | ||
| Original Estimate: | Not Specified | ||
| ODL Project: | coe |
| ODL Release: | |
| ODL Participation: | NOT_Integrated (UnManaged) |
| ODL Checkpoint: | Initial |
| ODL New Participation: | SNAPSHOT_Integrated (Managed) |
| Description |
SummaryCOE project requests to join the Fluorine release as a Managed Snapshot Integrated project. COE meets the requirements noted below. Healthy CommunityCOE has been active for the past two releases. Also, COE is becoming a key project for ODL due to industry momentum and adoption of Cloud native architecture. ResponsivenessThe committers in the COE team are active and regularly meet every week and also exhibit active code contributions. They respond to IRC and coe-dev emails promptly. Active CommittersThere are 8 committers in the COE team and most of them are active. TSC Attendance:COE project is well-represented in the TSC. One of the COE committers is TSC member and participate regularly in TSC meetings. More COE committers will join the TSC weekly meetings soon. Checkpoints Submitted On-Time:COE project has been always submitting release milestone reports on time and completing all release requirements. All deliverable for Oxygen can be seen here: http://docs.opendaylight.org/en/latest/release-process/milestone-readouts.html Jobs Required for Managed Projects Running:COE jobs snapshot : https://jenkins.opendaylight.org/releng/view/coe/
Depend only on Managed ProjectsCOE depends on following core and managed projects
DocumentationCOE User Guide and developer documents - https://wiki.opendaylight.org/view/COE:Main COE Team is working on adding more documentation
CLMCOE acknowledges that is required to handle Component Lifecycle Violations in a timely manner.
|
| Comments |
| Comment by Daniel Farrell [ 28/Mar/18 ] |
|
The "ODL New Participation" flag wasn't set, so this wasn't showing up in the filters the TSC was using to find applications to be Managed. The TSC can review the application next week. |
| Comment by Daniel Farrell [ 06/Apr/18 ] |
|
COE was approved as a Managed project in Fluorine (TSC vote). |